Find a district › Ansonia Local

Ansonia Local

What moved this district's funding from FY2025 to FY2027, line by line — on total state support, and on the foundation aid this site models — and where it sits among its county's districts.

Across Darke County Contents

FY2026 and FY2027 models, nominal dollars

On total state support, Ansonia Local moved +9.3% (+$801,841) from FY2026 to FY2027: the largest rise of 7 in Darke County.

Tri-Village LocalArcanum-ButlerLocalVersailles ExemptedVillageGreenville CityFranklin MonroeLocalMississinawa ValleyLocalAnsonia Local+9.3%−4.8%
Tri-Village LocalArcanum-Butler LocalVersailles Exempted VillageGreenville CityFranklin Monroe LocalMississinawa Valley LocalAnsonia Local+9.3%−4.8%
Tri-Village LocalArcanum-Butler LocalVersailles Exempted VillageGreenville CityFranklin Monroe LocalMississinawa Valley LocalAnsonia Local+9.3%−4.8%
The values
  • Ansonia Local: +9.3% (+$801,841) in total state support, FY2026 to FY2027
  • Tri-Village Local: +2.3% (+$160,482) in total state support, FY2026 to FY2027
  • Arcanum-Butler Local: +2.2% (+$196,196) in total state support, FY2026 to FY2027
  • Versailles Exempted Village: +0.2% (+$20,133) in total state support, FY2026 to FY2027
  • Greenville City: −2.8% (−$347,322) in total state support, FY2026 to FY2027
  • Franklin Monroe Local: −3.8% (−$160,094) in total state support, FY2026 to FY2027
  • Mississinawa Valley Local: −4.8% (−$329,258) in total state support, FY2026 to FY2027

On foundation aid, Ansonia Local moved +11.0% (+$833,641) from FY2026 to FY2027: the largest rise of 7 in Darke County.

Tri-Village LocalArcanum-ButlerLocalVersailles ExemptedVillageFranklin MonroeLocalMississinawa ValleyLocalGreenville CityAnsonia Local+11.0%−6.3%
Tri-Village LocalArcanum-Butler LocalVersailles Exempted VillageFranklin Monroe LocalMississinawa Valley LocalGreenville CityAnsonia Local+11.0%−6.3%
Tri-Village LocalArcanum-Butler LocalVersailles Exempted VillageFranklin Monroe LocalMississinawa Valley LocalGreenville CityAnsonia Local+11.0%−6.3%
The values
  • Ansonia Local: +11.0% (+$833,641) in foundation aid, FY2026 to FY2027
  • Tri-Village Local: +3.2% (+$194,786) in foundation aid, FY2026 to FY2027
  • Arcanum-Butler Local: +3.1% (+$243,042) in foundation aid, FY2026 to FY2027
  • Versailles Exempted Village: 0.0% ($0) in foundation aid, FY2026 to FY2027
  • Franklin Monroe Local: −4.7% (−$168,014) in foundation aid, FY2026 to FY2027
  • Mississinawa Valley Local: −4.9% (−$312,181) in foundation aid, FY2026 to FY2027
  • Greenville City: −6.3% (−$679,428) in foundation aid, FY2026 to FY2027

Every district the department attributes to Darke County, as a percentage of its own FY2026 figure, so a city and a village can be read on one scale. The two measures can rank the same county in different orders: a district held at its base does not move on foundation aid at all, whatever its other lines do.

By line Contents

Every line the department pays this district through, in the three years. Total state support, the last row, is all of them; foundation aid, the first, is the narrow measure — core foundation funding and the guarantee, the part this site models. FY2025 is the department's final payment report; FY2026 and FY2027 are its models of those years, not payments. Every figure is in nominal dollars.

Line FY2025 paidFY2026 modelFY2027 model FY2026 to FY2027
Foundation aid (the narrow measure)$7,092,383$7,560,596$8,394,237+$833,641
Transportation$766,082$762,242$721,401−$40,841
Special education transportation$79,374$92,450$92,354−$96
Preschool special education$119,177$125,205$123,165−$2,041
Supplemental targeted assistance (repealed by H.B. 96)$0$0$0$0
Formula transition supplement$0$0$0$0
Base funding supplement$0$18,689$28,635+$9,946
Enrollment growth supplement$0$0$0$0
Performance supplement$0$35,994$37,225+$1,231
Total state support (the wide measure)$8,057,016$8,595,176$9,397,017+$801,841

The lines sum to total state support in every year, to within cent rounding. Supplemental targeted assistance keeps its row after FY2025 because its going is part of the change: H.B. 96 repealed it, and the base funding and enrollment growth supplements it created are separate lines, not its replacement under another name.

The phase-in Contents

Foundation aid is paid as the funding base plus the The share of the gap between what the formula computes and a district's older base that is actually paid. A district below its base is held at the base, so a higher phase-in does not reach it.'s share of the gap between what the formula calculates and that base, and the guarantee holds it up where the result would fall. These are the department's own three figures for each year. FY2025 is the department's final payment report; FY2026 and FY2027 are its models of those years, not payments. Every figure is in nominal dollars.

Stage FY2025 paidFY2026 modelFY2027 model
Funding base$4,804,475$4,804,475$4,804,475
Calculated by the formula$8,236,166$8,111,953$8,394,237
Paid through the phase-in$7,092,383$7,560,596$8,394,237
Guarantee$0$0$0
Foundation aid$7,092,383$7,560,596$8,394,237
  • FY2025: +$2,287,908 above its base. The formula calculates $8,236,166, $3,431,691 over a $4,804,475 base, and the phase-in pays $2,287,908 of that gap.
  • FY2026: +$2,756,121 above its base. The formula calculates $8,111,953, $3,307,478 over a $4,804,475 base, and the phase-in pays $2,756,121 of that gap.
  • FY2027: +$3,589,762 above its base. The formula calculates $8,394,237, $3,589,762 over a $4,804,475 base, and the phase-in pays $3,589,762 of that gap.

The phase-in statewide counts the districts paid exactly their base in each year, which a higher rate does not reach, and what it paid above everyone else's.

What moved underneath Contents

Three inputs and the measure each reaches the dollars through. The files publish the inputs and the payment but not how much of the payment's change each input is, so nothing here divides the change between them. The FY2025 payment report carries no capacity inputs at all, so state share and enrollment start at FY2026. Dollar figures are in nominal dollars.

  • State share went from 67.3% in FY2026 to 65.2% in FY2027. It is the part of base cost the state pays after the district's local capacity is charged, so it reaches the dollars through foundation aid, which moved +$833,641 over the same two years. Reappraisal and the state share sets the fall beside every district's valuation change, by the share it started at.
  • Assessed valuation went from $118,086,840 in tax year 2023 to $121,157,142 in tax year 2025 (+2.6%). Valuation is the larger part of local capacity, which is what sets the state share above — the route by which a reappraisal reaches foundation aid at all.
  • Enrolled ADM went from 692.2 in FY2026 to 715.9 in FY2027, as each year's file states it (+3.4%). Base cost is computed per pupil, so enrollment reaches the dollars through the formula's calculated figure on the phase-in card.

Transfers and net funding Contents

What the department deducts from total state support before it pays the district — the educational service center's charge and other adjustments — and what is left. FY2025's report publishes the transfers as one total; FY2027's itemizes them; FY2026's publishes none, and that column says so rather than showing a zero. FY2025 is the department's final payment report; FY2026 and FY2027 are its models of those years, not payments. Every figure is in nominal dollars.

FY2025 paidFY2026 modelFY2027 model
Total state support$8,057,016$8,595,176$9,397,017
Service center chargenot itemizednot published−$342,957
Other adjustmentsnot itemizednot published−$35,249
Transfers, in total−$412,347not published−$378,206
Net state funding$7,644,668not published$9,018,811